The Cross Kirkland Corridor Isn't One Construction Project. It's Two, and They Don't Share a Deadline.

September 10, 2026

Anyone who runs, bikes, or walks the Cross Kirkland Corridor on a regular basis has developed a specific kind of fatigue this year. You come around the bend south of Totem Lake, expecting the same open gravel you've had for a decade, and instead there's fencing, steel plates, or a temporary pipe running alongside the trail like an oversized garden hose. You ask a neighbor when it's supposed to be done. Nobody has a straight answer, because the honest answer is complicated: there isn't one project to finish. There are two, run by separate public agencies, on two different clocks, and they happen to overlap on the same stretch of trail at the same time.

That distinction matters more than it sounds like it should. If you think of the CKC's disruption as a single event, you're waiting for a single finish line. If you understand it as two unrelated projects that collided, you stop waiting for a date and start tracking two dates, because the sewer emergency under the trail and the pedestrian bridge over it were never on the same schedule to begin with.

What's actually under the trail

The corridor runs 5.75 miles from the South Kirkland Park and Ride at the city's southern edge up through the Totem Lake Business District near Slater Avenue. Most of that distance is unremarkable in a good way: crushed gravel, a flat grade, glimpses of Lake Washington and the Seattle skyline through the trees. The trouble started in late July 2025, when King County and City of Kirkland crews found a leak in the Eastside Interceptor Section 14 pipe, a 7-foot-diameter sewer main that runs beneath the trail and carries an average of 10 million gallons of wastewater a day in dry weather on its way to King County's South Treatment Plant in Renton.

That's not a pothole. It's regional sewer infrastructure, and King County treated it that way. The county's Department of Natural Resources and Parks issued a Declaration of Urgency in September 2025 to fast-track repairs, and the City of Kirkland followed with its own Proclamation of Emergency. The trail segment between NE 52nd Street and 108th Avenue NE closed as early as January 5, 2026, while crews installed a 3,000-foot temporary above-ground pipe, 18 inches in diameter, to keep sewer service running to homes and businesses while they worked on the permanent fix underground.

The permanent repair finished first. King County confirmed the pipe work was complete and reopened that stretch of trail on February 23, 2026. It closed again for a single day on March 24 so crews could test soil conditions ahead of a second phase, then reopened that same evening at 5 p.m. That second phase is the one still shaping the trail as you read this: King County has said crews are returning this summer to stabilize a rockery wall and a culvert sitting beneath their pipe, and the temporary above-ground line, along with its fenced and steel-plated access points, is staying in place on the west side of the trail until that work wraps. Once it does, the equipment comes out and new trees go in.

So if you've walked past a length of exposed pipe near the corridor this year and assumed it was leftover from an unfinished repair, it's closer to the opposite. The emergency itself is resolved. What you're seeing is scaffolding for the next phase, not evidence the first one failed.

The bridge project near NE 85th Street

While King County was dealing with a sewer leak, the City of Kirkland and Sound Transit were already mid-construction on something unrelated: the NE 85th Street Shared-Use Pathway, a twelve-foot-wide walking and biking path meant to connect downtown Kirkland to the Rose Hill district and Sound Transit's new 405 Bus Rapid Transit station at I-405. The project broke ground on July 8, 2025, with Deputy Mayor Jay Arnold and several councilmembers on hand, and it includes a pedestrian bridge that spans directly over the Cross Kirkland Corridor near NE 85th Street.

Building a bridge over an active trail means closing the trail underneath it. That closure started around July 18, 2025, and Seattle Bike Blog described it as "months-long," with two posted detours: a shorter, non-ADA route east on NE 87th Street to 114th Avenue NE, and a longer ADA-accessible path down to 6th Street for anyone who couldn't manage the gravel shortcut. Kirkland's planning documents put the project's total cost near $12.17 million, with roughly $10.87 million coming from Sound Transit and the remainder from the city, and set a target of spring 2026 for completion.

Here's the part worth sitting with: the city's own Public Works page still lists both projects, the ESI-14 sewer repair and the NE 85th Street pathway, on its corridor-closures page. That listing alone doesn't mean either project is still closing the trail or has missed its target. Anyone hoping for a single "the trail is finally done" moment this fall is looking for a single finish date for two separate project timelines.

Separate project teams, distinct funding sources, two definitions of "finished"

ESI-14 Sewer Repair NE 85th Street Pathway
Lead agency King County (DNRP) City of Kirkland with Sound Transit
Cause Emergency leak, detected July 2025 Planned infrastructure, unrelated to the leak
Trail segment affected NE 52nd Street to 108th Avenue NE Near NE 85th Street
Funding County wastewater capital funds ~$10.87M Sound Transit, ~$1.3M city
Key 2026 milestone Permanent pipe repair complete, trail reopened Feb 23 Targeted spring 2026 completion
What remains Temporary above-ground pipe staying through summer culvert work Pedestrian bridge over the CKC

Reading these side by side is the whole point. One project is an emergency response to a failure nobody planned for. The other is a long-scheduled transit connector that happened to need the same twenty feet of trail. Their completion dates belong to separate schedules, and treating them as one continuous "CKC construction" story is exactly why the timeline has felt so hard to pin down.

What the trail still offers while you wait

None of this has actually closed the corridor's better stretches. South of Totem Lake, the trail slips back into tree cover and runs close enough to Google's Kirkland campus that you can watch the office lights come on at dusk. Crestwood Park sits just off the path with a spur trail and stairway leading up to it, a reliable stop if you need a bathroom break or a bench. Further along, a small sculpture of a frog scrambling over a fence marks an unofficial photo stop that longtime users treat as a mile marker. Near the old rail depot site, the Kirkland Rotary's pavilion preserves a short stretch of track and a vintage semaphore signal, a quiet nod to the line's original run as a passenger route until 1922 and its darker history as a 1942 gathering point for Japanese American residents ordered into wartime relocation.

Chainline Brewing sits directly on the trail near the southern stretch, which makes it one of the few businesses in Kirkland you can reach entirely on gravel, no road crossing required. Further north, the elevated Totem Lake pedestrian bridge, finished in 2023, solved what used to be the corridor's most confusing gap through the commercial district, and it's worth remembering that this wasn't always a smooth ride. The trail's more disruptive stretches are temporary. The good parts have been there the whole time and aren't going anywhere.

What this fall actually looks like

If you're planning a regular route on the CKC through September and into fall, expect the trail between NE 52nd Street and 108th Avenue NE to remain open but visibly under equipment, with the temporary pipe and fencing staying in place until King County finishes the rockery and culvert work it scheduled for summer. Near NE 85th Street, the bridge project had its own spring 2026 target, but the closures listing alone doesn’t show whether it remains underway or has missed it. Neither timeline is tied to the other, so don't expect one announcement to clear both.

Following a place this closely, down to which government agency owns which pipe, is part of what it takes to actually know a neighborhood rather than just visit it. That's the same instinct that shapes how the team at KLD Real Estate Group approaches every Eastside listing: the details that don't show up in a portal description are usually the ones that matter most once you live somewhere. If you're curious what else is changing in Kirkland this year, or you're weighing a move to the Eastside and want a local read on more than just school ratings and square footage, schedule your private consultation with KLD Real Estate Group.

Work With Us

At Kritsonis Lindor Real Estate Group, we understand that your home is more than just a property; it's a place where memories are made. That's why we're committed to providing you with a seamless and personalized real estate experience. Contact us today to learn more about how we can help you achieve your real estate goals.